Japan Nuclear Fukushima
FILE in In this Feb. 27, 2021, file photo, tanks (in gray, beige and blue) store water that was treated but is still radioactive after it was used to cool down spent fuel at the Fukushima Daiichi nuclear power plant in Okuma town, Fukushima prefecture, northeastern Japan. Technicians at Japan's wrecked Fukushima nuclear power plant neglected to investigate the cause of faulty filters that were discharging dangerously radioactive water into the sea, company officials admitted Tuesday, Sept. 14, 2021, after being forced to repair the filters. (AP Photo/Hiro Komae, File)
national

Fukushima plant failed to probe cause of faulty filters

7 Comments
By MARI YAMAGUCHI

Officials at Japan's wrecked Fukushima nuclear power plant have acknowledged they neglected to investigate the cause of faulty exhaust filters that are key to preventing radioactive pollution, after being forced to replace them twice.

Representatives of the operator, Tokyo Electric Power Company Holdings, made the revelation Monday during a regular review of the Fukushima Daiichi plant at a meeting with Japanese regulatory authorities. Three reactors at the plant melted following a massive earthquake and tsunami in 2011.

The filters are designed to prevent particles from escaping into the air from a contaminated water treatment system — called Advanced Liquid Processing System — that removes selected radioactive isotopes in the water to below legal limits.

“At the core of this problem is TEPCO’s attitude,” a Nuclear Regulation Authority commissioner, Nobuhiko Ban, said at the meeting.

TEPCO has been repeatedly criticized for coverups and delayed disclosures of problems at the plant. In February, it said two seismometers at one reactor had remained broken since last year and failed to collect data during a powerful earthquake.

Company officials said that 24 out of 25 filters attached to the water treatment equipment had been found damaged last month, after an alarm went off as workers were moving sludge from the unit to a container, temporarily suspending the water treatment. The operation partially resumed last week after the filters were replaced.

TEPCO said it had detected similar damage in all of the filters two years ago, but never investigated the cause of the problem and did not take any preventive steps after replacing the filters.

Another regulatory commissioner, Satoru Tanaka, said at the meeting that the utility company should have responded to the problem more quickly to minimize the risk of possible radiation leakage into the environment.

TEPCO officials said dust monitors indicated no radiation leaks to the outside or exposure to plant workers inside the water treatment facility.

Akira Ono, head of TEPCO's decommissioning unit, said he regretted the utility's failure to address the problem earlier. He promised to improve safety management.

Japanese officials are working with the International Atomic Energy Agency to prepare to discharge into the ocean the wrecked plant's cooling water, treated so its radioactivity levels are below legal limits. Slated to start in spring 2023, the controversial plan is fiercely opposed by Fukushima’s fishing community, as well as local residents and nearby countries.

Fully decommissioning the nuclear plant is expected to take decades, experts say.

© Copyright 2021 The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed without permission.

©2021 GPlusMedia Inc.

7 Comments
Login to comment

The Japanese culture of obscurity and cover ups is not gonna work this time.

-1 ( +1 / -2 )

The majority concern with TEPCO is its lack of transparency.

The nuclear disaster clean up is not decommissioning. Eventually cost more than ¥80 trillion and 100 years.

3 ( +3 / -0 )

TEPCO said it had detected similar damage in all of the filters two years ago, but never investigated the cause of the problem and did not take any preventive steps after replacing the filters.

Radioactive pollution ongoing and building up in the environment.

Who could have imagined?

1 ( +2 / -1 )

When are TEPCO management going to start going to Jail for this insanity?

They knew they were broken and did nothing. Surely that is a crime!!!???

1 ( +1 / -0 )

Does that mean, it’s all again silently blown contaminating into the air, and then with load propaganda cleanly led into the sea? Something like that? Correct me, if I understood that wrong and that’s not the essence of what has been revealed.

1 ( +1 / -0 )

WOW!! I am totally surprised and flabbergasted at this unprecedented information that TEPCO were found to have a terribly lax attitude towards safety issues at their crippled and melted nuclear power plant.......

1 ( +1 / -0 )

"...Akira Ono, head of TEPCO's decommissioning unit, said he regretted the utility's failure to address the problem earlier. He promised to improve safety management..."

Well as long as you showed the appropriate regret and you pinky promise that you will of course improve the safety management then all is forgiven Akira.......as you were

1 ( +1 / -0 )

Login to leave a comment

Facebook users

Use your Facebook account to login or register with JapanToday. By doing so, you will also receive an email inviting you to receive our news alerts.

Facebook Connect

Login with your JapanToday account

User registration

Articles, Offers & Useful Resources

A mix of what's trending on our other sites